<<< Loan No. and Title: SLP/88 Pro-Poor Rural Development Project - Hambanthota District ...>>>Project Goal is Reduce Rural Poverty and Mitigate regional inequality


Background and the Rationale of the Pro-Poor Rural Development Project
The government of Sri Lanka (GOSL) announced its new policy framework " Mahinda Chinthana " in November 2005. This policy framework stated that the Government would focus on poverty alleviation programmes in rural areas and reduces regional disparities.

Under this policy, the Government of Sri Lanka initiated a new community participation programme called "Gama Neguma" in 2006. This program amis at improving basic infrastructure such as electricity, communication network, water supply, roads,health centers, preschools, community centers and others in rural areas based on community needs. Under the initative of Ministry of Nation Building, 119 target villages have been selected and the projects under " Gama Neguma" were identified through consultation with rural community. These projects will be implemented first in 119 villages in 2006, and will be expanded to 14,000 villages throughout the country.

As in the case of Gama Naguma programme, The Pro-Poor Rural Development Project aims at reducing poverty in rural areas mainly by developing infrastructure. During project formulation, to identify the needs of community and to select sub-projects to be implemented under the project, a number of consultations were held in the rural areas with the local authorities such as Pradeshiya Shabas, Divisional Secretariats, and Provincial Councils.

OBJECTIVE OF THE PROJECT
The Objective of the Project is "to reduce rural poverty and mitigate regional inequality by enhancing the accessibility to economic and social services through improvement of roads in selected districts"
Scope of the Project
Project covers construction, rehabilitation and improvement of road network in Hambanthota District.

Provincial Roads: 67.00 Km National Roads:121.00 Km (Continuation SIRUP Sub - Project by RDA)

The sub-projects have been selected according to the criteria below.
1. Roads that contibute to increase economic opportunities

2. Roads connnecting the selected villages with rural market places, banks,and commmunication services.

3. Roads the selected villages with B or C class roads.

4. Roads connecting villages withing the DS divisions, and

5. Roads connecting the DS Divisions with District Township.


Project Duration 2007-2009

Project Goal:
PROJECT OUTCOME
1. Mitigate regional inequality Increase the accessibility and mobility in the Project areas.
2. Reduce Rural Poverty
Loan Amount: Total in SLR
By JBIC Rs. 3597 Million
By Sri Lanka Rs. 1219 Million
Rs. 4816 Million


Cost Estimate for Hambantota Roads:

Rs. 236 million / Yen 264 Million


Targat areas: Targat D.S. Divisions
Rural Roads 1. Lunugamvehera
Drinking Water Supply & Sanitation 2. Sooriyawewa
Electricity 3. Aagunukolapelessa
Irrigation 4. Katuwana
5. Walasmulla
6. Weeraketiya
7. Okewela

OUTPUTS >>>
Improve rural infrstructure facilities with community participation in road, water supply, electrification and irrigation


Project Period
3 years from 2007 Requst from JBIC: Local competitive Bidding ( Open tender ) is must for all the sub Projects.
Pro- Poor Rural Development Project at Hambantota. ### Current Stage ###
Funds are leased for > 11 Roads
64.2 Km
Rs. 181 million ( for Road works )
Awaiting for approval > 02 Roads
3.2 Km
Rs.9 Million
Road work started on > 07 Roads
To be started > 03 Roads
At Negotiation stage > 01 Road
Total > 11 Roads
Expenditure as at the end of 2007 for Road works > Rs. 11 Million
Estimated Expenditure for the month of January 2008 > Rs. 28 Million



Implementation Schdule for the sub- projects for the 1st year.

1. Sign of the Loan agreement: > May- April,2007
2. Detail design/ Tender Documentation/ Tender selection of the contactors > May -June, 2007
3. Civil work start > june- July, 2007


Road Sub Project Schedule

Ref No. Sub Project No. Name of Road Length(Km) DS Division Scope of Construction Project Cost (Rs,) Rev. Pro. Cost(Rs.) Rev. Length(Km) Agreement Amount Remarks(as at 31/01/2008)
1 HR1 Mandaduwa Kapugampotha Road 2.2 Weeraketiya Rehabilitation 17,100,000.00 12,325,600.00 2.0 8,142,068.31
2 HR18 Udagomadiya, Kandekumbura, Dangalakanda obadagahadeniya 10.0 Katuwana Rehabilitation 29,200,000.00 32,661,000.00 5.7
3 HR 27 Rammale tea factory to Hundugala via saputhanthrikanda & Egodabadda 13.0 Walasmulla Rehabilitation 32,800,000.00 33,232,000.00 8.8 23,001,540.50
4 HR 38 Mahapelassa Juction to Unudiya Pokuna 5.7 Sooriyawewa Rehabilitation 15,700,000.00 17,086,500.00 4.0 13,067,749.49
5 HR 39 Meegahajadura School to Padikemgala Temple Road 5.0 Sooriyawewa Rehabilitation 14,800,000.00 16,660,500.00 5.0 11,003,611.50
6 HR 44 Weerawila Juction to Weerawila pola Juction 1.5 Lunugamwehera Rehabilitation 2,800,000.00 4,872,300.00 1.7 4,213,025.55
7 HR 45 Nirosha Kade on wellawaya Road to Kudagam yaya via Pannegamuwa. 6.5 Lunugamwehera Rehabilitation 20,400,000.00 24,741,300.00 6.0 16,261,715.69
8 HR 52 Binkama to Rathmalwala 15.0 Angunukolapelassa Rehabilitation 58,300,000.00 70,400,000.00 15.5 49,070,516.25
9 HR 63 Kandahena kade to Kadigamuwa road via Wawwa 9.0 Okewela Rehabilitation 44,500,000.00 32,152,500.00 3.5 24,357,908.02
10 HADD 10 Welipitiya to Siyarapitiya 9.0 Katuwana Rehabilitation 22,600,000.00 30,137,000.00 9.0 21,469,285.10
11 HADD 11 Talawa to Kariyamadiththa Road. 4.5 Angunukolapelassa Rehabilitation 12,800,000.00 14,667,400.00 3.0 10,478,375.65
81.4 271,000,000.00 288,966,100.00 67.4 181,065,796.06


Project Management Unit (P.M.U.)
The P.U.M. set-up in the National Planning Department ( N.P.D.) in Ministry of Finance & Planning.
National Steering Committee Provincial steering Committee
Consult of -Department of National Planning
Department of External Resource
Department of National Budget
Finance Commission
Road Development Authority
Japan Bank for international Co-operation
Chief Secretaries of 3- Provincial Council
District Secretaries of 4 District
Consult of -Chief secretary
District Secretary
Deputy chief secretary (Finance)
Deputy chief secretary (Planning)
Secretaries – Provincial Ministry of roads
Divisional Secretaries of relevant
District planning Director
General Manager (PRDA / PRDD)
Chairman of relevant pradeshiya sabha
P.I.U. Manager

Office Staff (PMU)
S.No. Designation Officer Name Address Tel/ Fax No.
01. National Project Director Mr. S. Pulukkopdi
02. Team Leader/Project Management Consultant Mr. T.G. Jayasinghe
Staff (PIU)
03. Project Manager
Mr. T.H.D. Chandrasena
No 05, House 35 Road, Indivinna House Scheme, Hambantota.
047-2220715
04. Project Engineer Mr. K.B.G. Maduwage 0602474041
05. Project Accountant Mr. W.C. De Mel 047-2220715
06. Project Monitoring & Administrative Officer Mr. W.J.K.V. Ranjith 0602474041
07. Project Management & Monitoring Consultant Mr. R.B. Piyadasa
08. Computer Oparators: Miss T.A. J. Udayanganee
Miss L.A. Shyamali

Southern Provincial Council